2. External Walls


a. Ground floor to wall junction

Key Points:

  • Photograph should show moisture resistant insulation fitted above damp-proof course level and extend to the block/structure.
  • Ensure insulation (or the clear cavity where blown insulation would go) is visible.

Photo Reference – P2/2a

SAP PSI junction reference – E5

Example 2.a Photograph (Cavity for Blown Insulation):

Example 2.a Photograph (Filled Cavity):

Guidance for Timber Frames 2a

a. Ground floor to wall junction

Key Points:

  • Photograph should show moisture resistant insulation fitted above damp: proof course level and extend to the foundation block/structure.
  • Ensure insulation (or the clear cavity where blown insulation would go) is visible.

Photo Reference – P2/2a

SAP PSI junction reference – E5

Example 2.a Photograph (Cavity for Blown Insulation):